Water
insulation of tanks and swimming pools
Equipment
before starting insulation:
• Block and
concrete should be covered with a soft layer until the back of the block
• The floors
should be clean and dust free
• Create a
concrete corner all over the perimeter when the walls meet the floor with a
thickness of 5 cm * 5 cm
• In the
case of a skimmer for swimming pools, a scimer house must be made in the block
wall, with no skimmer installed before isolation.
Work steps
Primer coat paint is completely flat and
waiting to dry (primer paint drying can take place within 24 hours or more
depending on the temperature).
• Install
the first layer of insulation with a total weld while preserving the overlap
between the layers and not less than 100 to 150 mm between the longitudinal and
transverse weld lines.
Installing
the second layer according to the manufacturer's instructions.
• Install
protection panels on the walls and the places required for that, according to
the site’s requirements.
After
insulation:
A concrete
layer should be placed to protect the floors with a thickness of not less than
10 cm within 24 hours after the completion of the isolation work and before the
mourning goes to work on site.
Do not test
the tank or the pool until after the completion of the work of pouring
reinforced concrete for floors and walls, while maintaining the insulation tip
on the back of the block.
The tank or
the pool should not be filled with water from the inside until after the burial
place is finished around the tank and the pool, as this may cause the block
wall and the insulation layer to collapse together.
When testing
from the outside, the water level must not exceed the highest point of the
waterproofing layer.
The roof of
the tank must be isolated in the case of the cultivation of ponds and so on
above the tank
If any
modification occurs to the wall of the tank or the pool, coordination with the
company should be made to make the necessary precautions to deliver the
insulation, otherwise the company guarantee will expire.
Illustration
model for the water tank system of swimming pools and pools:
1. Concrete
hygiene.
2. Cement
corner
3. Primer
primer for walls and floors.
4.
Preliminary layer of bituminous insulation.
5. A second
layer is a bitumen coil buffer.
6. A
concrete layer for floor protection of not less than one cm.
7.
Reinforced concrete.
8. Wall
Protection Layer (reinforced bitumen boards or fiberboard)